Project

General

Profile

Stabilisation process » History » Version 2

Greg Burri, 11/06/2009 03:28 PM

1 1 Greg Burri
h1. Stabilisation process
2
3
These process involves during the alpha and beta phases. It consists to try to find and resolved a maximum of bug.
4
5 2 Greg Burri
# Take a look in the bug list, if there is some of them tagged as _Urgent_ or _Critical_ and you are able to resolve it (you know the component involved) then try to fix them.
6 1 Greg Burri
# If there is no bug to resolve, play freely with the software, do anything you want, try to use it in the most unconventional way.
7
# If you detect an anomaly :
8
## Try to locate the component and the chunks of code involved
9
## If it's a critical bug and you know the component try to resolve it immediately
10
## Else insert it as a new issue in the bug tracker. Write a maximum of functional and technical details. It's very important to write the way to reproduce it.